Most construction claims in Vietnam do not start with the main contractor; they start two tiers down, where a poorly vetted trade package fails and the employer discovers that its only counterparty is a contractor with limited assets. Subcontracting construction Vietnam is therefore less a procurement convenience than a risk-transfer mechanism that either holds or collapses, depending on how the main contract, the subcontract and the 2026 legal framework fit together. The pattern repeats from an airport terminal fit-out to a solar farm or a resort complex.

This article is for foreign investors, lenders, EPC contractors and in-house counsel who sign, finance or administer projects in Vietnam. It explains who answers for a subcontractor, when the employer may intervene, how nominated subcontractors and direct payment work, and what changes when the main contractor is a foreign entity.
Legal framework for subcontracting construction Vietnam in 2026
Three instruments now govern subcontracting construction Vietnam projects. The Law on Construction No. 135/2025/QH15 (Luật Xây dựng) took effect on 1 July 2026. Decree 210/2026/NĐ-CP, which guides the Law on construction contracts and replaces Decree 50/2021/NĐ-CP, took effect on the same date. Decree 212/2026/NĐ-CP on construction capacity conditions governs foreign contractors from 1 July 2026.
Decree 210 classifies contracts by relationship as well as by scope and price. A “main contract” and a “subcontract” (including a nominated subcontract) are separate categories, as are internal assignments of work and contracts with a foreign element. The practical point is that a subcontract is a full contract in its own right and must contain the mandatory content that the decree prescribes for construction contracts generally.
For subcontracting construction Vietnam practice, the decree states the central rule in plain terms. The parties agree whether and how subcontracting is permitted, but the main contractor may only enter into a subcontract for work that matches the subcontractor’s actual capacity. The main contractor remains responsible to the employer for progress, quality, occupational safety and environmental compliance, for its own defects and for those of its subcontractors. A subcontractor takes on the rights and obligations of the contractor for its own scope.
Why the main contractor cannot “outsource” responsibility
The Law on Construction reinforces this from another direction: where a breach is caused by a third party, the party in breach still answers to its counterparty. For an employer this is the legal foundation of the whole structure. A late subcontractor is the main contractor’s problem first, and the employer’s delay damages claim runs against the main contractor, not against the trade package.
For a main contractor the inverse is equally important. Liability to the employer is not reduced by the subcontractor’s insolvency, so the subcontract must be built to pass risk down: back-to-back scope, matching defects periods, a performance security from the subcontractor and a right to step in.
Public investment and PPP projects: tighter rules on who may be engaged
Decree 210 draws a hard line between private and public capital. On privately funded projects the parties set the subcontracting regime by agreement. On public investment projects, the decree requires subcontracts to be awarded in line with the procurement legislation, and the main contractor needs the employer’s written consent to use a subcontractor that is not on the list attached to the main contract.
This scope point matters for every number or procedure below that is described as “public investment or PPP”. Those rules do not automatically bind a private developer, although a prudent private employer may well copy them into its own contract. The Law on Public-Private Partnership and the 2023 Law on Bidding are named here for completeness; their detailed subcontracting provisions are outside the scope of this article.
| Issue | Private-capital project | Public investment or PPP project |
|---|---|---|
| Right to subcontract | As agreed in the contract | Subcontracts awarded under procurement legislation |
| Subcontractor outside agreed list | As agreed in the contract | Employer’s written consent required |
| Effect of nominating a subcontractor | Contract price consequences as agreed | Nomination does not change the main contract price |
| Direct payment to subcontractor | If agreed | If agreed and requested by the main contractor |
| Responsibility to employer | Main contractor | Main contractor |
FIDIC 1999 edition: how clause 4.4 frames subcontracting
Most foreign-funded projects involving subcontracting construction Vietnam use a FIDIC-based form, so it is worth comparing the national rule with the FIDIC 1999 edition. In the Silver Book (EPC/Turnkey), sub-clause 4.4 prohibits subcontracting the whole of the Works and makes the contractor responsible for the acts and defaults of a subcontractor, its agents and employees as if they were the contractor’s own.
The same sub-clause provides that, where the Particular Conditions so specify, the contractor must give the employer at least 28 days’ notice of the intended appointment of a subcontractor with details of its experience, of the intended start of the subcontractor’s work and of its start on Site. Notice is a transparency mechanism, not an approval right. If the employer wants a veto, the Particular Conditions must say so.
Sub-clause 4.5 deals with nominated subcontractors, who are appointed by instruction under the variations clause. The contractor is not obliged to employ a nominee to whom it raises a reasonable objection, supported by particulars, as soon as practicable. This is close in spirit to Decree 210, which allows a main contractor to refuse a nominated subcontractor in defined circumstances.
We cite the FIDIC 1999 edition only; a 2017 second edition exists with different wording.
Subcontracting construction Vietnam: gaps a FIDIC form leaves open
A FIDIC form assumes a common-law style of contracting and a neutral Engineer. In Vietnam, three gaps recur. First, the notice period under sub-clause 4.4 does nothing for a project that needs the employer’s consent under Vietnamese procurement rules. Second, the form is silent on the content a subcontract must carry under Decree 210. Third, direct payment to subcontractors is a Decree 210 feature for which the FIDIC 1999 Silver Book contains no express mechanism that we have identified.
Lenders financing subcontracting construction Vietnam chains should ask whether the Particular Conditions have been conformed to Vietnamese law, because an amended form that conflicts with mandatory provisions invites argument at the worst moment.
Nominated subcontractors in subcontracting construction Vietnam: when the employer may impose a choice
Decree 210 permits an employer to designate a subcontractor, but only in situations that the main contract lists specifically. The trigger is not general dissatisfaction; it is that the main contractor has failed to meet safety, quality or progress requirements after the employer has asked it to do so.
The main contractor may refuse a nominee where the nomination falls outside the agreed situations, where the main contractor’s own work is still performed in line with the contract, or where there is a reasoned basis to believe that the nominee cannot meet the requirements. On public investment and PPP projects, the decree adds that a nomination does not change the contract price payable to the main contractor.
- Employer: draft the nomination triggers narrowly and attach a clear performance-failure procedure, otherwise the right is hard to exercise.
- Main contractor: record any reasoned objection in writing at once, and reserve time and cost relief where the nominee’s performance later falls short.
- Lender: check whether the project budget carries any contingency for a nomination, because on private projects price consequences depend entirely on the contract.
Market practice is to pair a nomination right with a tripartite novation or collateral warranty so that the employer holds a direct claim against the nominee. We note that this is market practice, not a statutory requirement.
Direct payment to the subcontractor and payment security
Decree 210 allows the employer to pay a subcontractor directly, on the main contractor’s proposal and as agreed in the contract. This is useful where a key supplier is at risk of stopping work because the main contractor is slow to pay down the chain, but it introduces its own risks.
A direct payment must be reconciled to the main contractor’s account so that it does not pay twice. It should be recorded as payment of the main contractor’s debt, not as a new obligation of the employer. Where the employer has withheld retention from the main contractor, the subcontract should state whether a proportionate retention is also withheld from the subcontractor.
Payment currency also needs thought. Under the Law on Construction, contract payment is in Vietnamese dong, and foreign currency may be used only in compliance with foreign exchange law. A foreign main contractor that agrees a foreign-currency subcontract should confirm the permitted basis first.
Is your subcontracting chain structured to hold the risk you intend to transfer? IVLF Advisors offers a confidential preliminary review (under NDA) of your main contract and subcontract forms before the next award.
Foreign main contractors: the Vietnamese subcontractor requirement
Subcontracting has an additional dimension when the main contractor is a foreign entity. Under Decree 212/2026, a foreign contractor must either form a joint venture with a Vietnamese contractor or use Vietnamese subcontractors, unless no domestic contractor has the capability to perform any part of the package. The application must state clearly the scope, quantity and value of the work that goes to the Vietnamese party.
This requirement is a licensing condition. It follows that a foreign main contractor cannot treat its Vietnamese subcontractor as a commercial afterthought: the licence application must annex either the joint venture agreement or the principal or framework subcontract with the Vietnamese subcontractor. After the licence is issued, the contractor must carry out the Vietnamese subcontract it identified, and the employer or main contractor that engaged the foreign party is expected to supervise that commitment. We cover the licence itself in our guide to the construction licence for foreign contractors in Vietnam.
A foreign contractor that wants to share risk and bid together, rather than subcontract, should review the alternative described in our article on joint ventures of contractors in Vietnamese bidding.
Choosing between a joint venture and subcontracting construction Vietnam work
| Factor | Joint venture with a Vietnamese contractor | Vietnamese subcontractor |
|---|---|---|
| Liability to employer | Shared by members under the JV arrangements; check joint liability wording | Main contractor alone |
| Control of the Vietnamese scope | Shared, through the lead member and JV agreement | Full, through the subcontract |
| Licensing evidence | JV agreement with the Vietnamese partner | Formal or framework subcontract |
| Performance security | Each member by its share, or the lead member if so agreed | Subcontractor posts to main contractor as agreed |
| Best suited to | Shared design, shared bidding strength | Clearly separable local scope |
Drafting checklist for a subcontract that holds up
Whatever the project’s funding, a robust subcontract for subcontracting construction Vietnam work should address the following points in terms that mirror the main contract.
- Back-to-back scope and standards: the same specifications, quality plans, testing, acceptance and defects periods as the main contract.
- Capacity representation: a warranty of capability and licensing, supported by the information the subcontractor publishes about its capacity. Since the 2025 reform, organisational capacity is self-disclosed on the national construction database, and the employer is responsible for its own selection, so independent checks of the contractor’s record matter.
- Security: a performance guarantee and, where relevant, advance payment security, issued by a credit institution.
- Payment mechanics: payment terms, retention, set-off, and whether direct payment from the employer is available.
- Termination and step-in: a right to take over the subcontract or have it assigned to the employer if the main contract is terminated. FIDIC 1999 sub-clause 15.2 contemplates the contractor complying with reasonable instructions on assigning subcontracts after termination.
- Insurance and safety: allocation of insurance responsibility, consistent with the mandatory insurance rules under the Law on Construction and its implementing decree.
- Disputes: a forum aligned with the main contract, to avoid parallel proceedings with inconsistent outcomes.
The national database csdlhdxd.gov.vn is where organisations publish their capacity information, and the FIDIC website lists the standard forms referred to above. Treat it as a starting point for due diligence, not as proof.
Assignment, change of subcontractor and contract termination
Subcontracting is not the same as assigning the contract. Under Decree 210, transferring the contract to a third party without the other side’s consent is one of the serious breaches that may justify termination. A main contractor that hands the whole project to another entity risks exactly that outcome, and FIDIC 1999 sub-clause 4.4 likewise prohibits subcontracting the whole of the Works.
Sub-clause 1.7 of the same form bars assignment without the other party’s prior agreement, with an exception for assigning, as security for a bank or financial institution, the right to moneys due under the contract. For lenders this exception is the usual route to taking security over receivables.
Where a public investment project requires written consent to replace a subcontractor, the employer’s silence should not be read as approval.
Practical risks of subcontracting construction Vietnam for each party
For employers, the main exposure is a subcontract chain too long to supervise and a main contractor that passes on risk but not capability. Require a list of approved subcontractors, a notice obligation for substitutions and the right to inspect subcontract terms.
For main contractors, the main exposure is the mismatch between the main contract and the subcontract in liquidated damages, defects periods and force majeure. Where the main contract allows relief for a change in law or unforeseeable ground conditions, the subcontract must give the subcontractor only corresponding relief, and only on the same notice timetable.
For lenders, the exposure is concentration: one subcontractor holding a critical package without a replacement plan. Lenders should ask for step-in rights, collateral warranties and evidence that the subcontractor’s key personnel meet the professional qualification requirements imposed on individuals under the Law on Construction.
A hypothetical example illustrates the point: an employer on a private EPC project learns that the electrical package has been sublet to a company with no track record. Without a notice obligation and an approved-subcontractor list in the contract, the employer’s remedy is limited to a claim against the main contractor once the package fails.
How Subcontracting Construction Vietnam Applies Across Project Types: Infrastructure, Industry, Energy and Real Estate
The depth of the subcontract chain and the identity of the employer differ widely by sector, and so do the controls that matter.
Infrastructure and transport
Expressways, ports, metro, high-speed rail stations and airport terminals are often State-owned or PPP, so the public investment rules on engaging subcontractors often apply; classification depends on the funding source and depends on the funding source of each project. Large programmes such as the North–South high-speed railway (about 1,541 km, Hanoi to Ho Chi Minh City) or the Long Thành International Airport phase 1 terminal (commercial operation expected from 24 December 2026, according to press reports) rely on many tiers of specialist work, which makes consent rights and flow-down obligations especially important.
Heavy industry and factories
For steel, petrochemical and cement plants and FDI factories, the parties’ agreement governs. Specialist foreign vendors and local civil subcontractors often meet at the interface, so subcontracting construction Vietnam clauses should align warranties, performance guarantees and testing responsibility.
Renewable energy and power
Solar, wind, grid and gas-to-power projects often use nominated or owner-preferred equipment suppliers. The treatment depends on the contract structure, so lenders will ask how direct payment and step-in rights interact with security over the project.
Real estate and mixed-use
Hotels, resorts, urban areas and mixed-use complexes use many trade packages and local labour. Payment discipline down the chain protects completion dates, and a direct-payment mechanism can keep key trades on site if the main contractor is in difficulty.
| Sector | Typical contract or risk feature | What to check |
|---|---|---|
| Expressway, rail station, airport terminal | Public or PPP elements likely; deep subcontract chain | Consent rules; flow-down; capacity disclosure |
| Steel, petrochemical, cement, factory | Private; foreign and local vendors | Warranty alignment; testing responsibility |
| Solar, wind, grid, gas-to-power | Fact-specific; nominated suppliers | Direct payment; step-in; lender security |
| Hotel, resort, urban area | Private; many trade packages | Payment discipline; replacement of defaulting trade |
These are hypothetical categories, not real projects. In each, the main contractor remains answerable for its subcontractors unless the contract validly provides otherwise.
Conclusion
Subcontracting construction Vietnam works when the main contract allocates responsibility clearly, the subcontract mirrors it, and any foreign element has been licensed correctly. The practical next step is to audit your current subcontract template against the main contract, the Decree 210 content requirements and, for foreign contractors, the Decree 212 licence conditions, and to correct gaps before the next package is awarded.
Frequently Asked Questions
Can a main contractor subcontract the entire project in Vietnam?
Not safely. The FIDIC 1999 edition prohibits subcontracting the whole of the Works, and handing the contract to a third party without consent can amount to a serious breach under Decree 210. Contract terms should state the permitted limits.
Is the main contractor liable for its subcontractor’s defects?
Yes. Under Decree 210 the main contractor answers to the employer for progress, quality, safety and environmental compliance, including the defaults of its subcontractors. Its recourse is against the subcontractor under the subcontract.
Can the employer pay the subcontractor directly?
Yes, if the contract allows it and the main contractor proposes it. Decree 210 provides for direct payment, so the contract should say how such payment is recorded against the main contractor’s account.
Does a foreign contractor need a Vietnamese subcontractor?
Generally yes. Decree 212/2026 requires a foreign contractor to partner with a Vietnamese contractor, as joint venture member or subcontractor, unless no domestic contractor can perform any part of the package.
Do the Decree 210 public-sector subcontracting rules apply to private projects?
No, not automatically. The consent and procurement requirements apply to public investment and PPP projects; private projects follow the parties’ agreement, though employers often adopt similar controls by contract.
Disclaimer: this article provides general information and is not legal advice for a specific matter. The law is stated as at 22 October 2026. Please obtain advice on your own facts before acting.